AISD Maintenance Projects
Gymnasium Floor Replacement
Location: Amarillo High Old Main Gym
Start: April 30, 2001
Finish: June 15, 2001
Architect: Shiver-Megert & Associates
Contractor: Plains Builders
Project Cost for 3 Schools: $334,889.00
Gymnasium Synthetic Floor Replacement
Location: Caprock & Tascosa High School Activity Centers
Start: April 30, 2001
Finish: July 21, 2001
Architect: Shiver-Megert & Associates
Contractor: Plains Builders
Project Cost for 3 Schools: $334,889.00
Softball/Football Rebel Park Renovation
Location: Tascosa Rebel Park
Start: March 12, 2001
Finish: July 24, 2001
Architect: Turner Land Architecture
Contractor: Plains Builders
Project Cost: $294,505.00
Baseball Backstop
Location: Tascosa High School
Start: August 23, 2001
Finish: September 21, 2001
Architect: Shiver Megert & Associates
Contractor: Western Fence Company
Project Cost: $9,740.00
Lighting/Dimmer System Replacement
Location: Amarillo High School and Tascosa High School Auditoriums
Start: April 27, 2001
Finish: August 17, 2001
Architect: Shiver-Megert & Associates
Contractor: A-1 Electric
Project Cost: $252,448.00
Hail Damage/Roof Repairs
Location: Sleepy Hollow Elementary School
Start: April 30, 2001
Finish: July 31, 2001
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $305,000.00
Hail Damage/Roof Repairs
Location: Belmar
Start: April 30, 2001
Finish: July 31, 2001
Architect: Shiver-Megert & Associates
Contractor: Schrader Roofing
Project Cost: $249,400.00
Roofing and Waterproofing Repairs
Location: Bowie Middle School
Start: July 12, 2001
Finish: January 31, 2002
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $568,000.00
Roofing and Waterproofing Repairs
Location: Avondale Elementary School
Start: August 23, 2001
Finish: December 31, 2001
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $243,000.00
Roofing and Waterproofing Repairs
Location: Oakdale Elementary School
Start: September 18, 2001
Finish: January 31, 2002
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $334,000.00
Roofing and Waterproofing Repairs
Location: Forest Hill Elementary School
Start: September 27, 2001
Finish: January 31, 2002
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $240,000.00
Roofing and Waterproofing Repairs
Location: Mesa Verde Elementary School
Start: October 23, 2001
Finish: March 31, 2002
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $231,000.00
Roofing and Waterproofing Repairs
Location: Eastridge Elementary School
Start: October 30, 2001
Finish: March 31, 2002
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $270,000.00
Roofing and Waterproofing Repairs
Location: Fannin Middle School
Start: November 13, 2001
Finish: May 31, 2002
Architect: Shiver-Megert & Associates
Contractor: Construction Services
Project Cost: $551,000.00
Asbestos Abatement and Renovation
Location: San Jacinto Elementary School
Start: June 2, 2001
Finish: August 15, 2001
Architect: WD Architects
Contractor: TEC Construction
Project Cost: $179,559.20
Hallway Lighting Project
Location: Crockett and Fannin Middle Schools
Start: February 8, 2001
Finish: April 20, 2001 ** Extended Until May 31, 2001
Electrical Engineers: Reynolds Engineering Associates
Contractor: Coronado Electric
Project Cost: $24,995.00
Tech Lab Renovation
Location: Tascosa High School
Start: July 18, 2001
Finish: August 24, 2001
Architect: Shiver-Megert & Associates
Contractor: North Line Construction
Project Cost: $24,997.00
Renovation of Counseling Offices
Location: Palo Duro High School
Start: July 18, 2001
Finish: August 24, 2001
Architect: Shiver-Megert & Associates
Contractor: North Line Construction
Project Cost: $24,866.00
SLC Classroom
Location: Horace Mann Middle School
Start: September 26, 2001
Finish: December 7, 2001
Architect: Shiver-Megert & Associates
Contractor: TEC Construction
Project Cost: $27,800.00
Tascosa Baseball Fence
Location: Tascosa High School
Start: September 28, 2001
Finish: December 11, 2001
Architect: Shiver-Megert & Associates
Contractor: Reynosa Construction
Project Cost: $50,900.00
Cast Stone Repairs
Location: Margaret Wills Elementary
Start: December 5, 2001
Finish: December 31, 2001
Architect: Shiver-Megert & Associates
Contractor: Broadus Masonry Inc.
Project Cost: $4,835.00
Parking Lot Paving Project
Location: District Wide
Start: March 11, 2002
Finish: September 30, 2002
Architect: Shiver-Megert & Associates
Contractor: Fuller & Sons Construction, Inc.
Project Cost: $557,581.89
Ag Farm Fence Project
Location: AISD Ag Farm
Start: January 9, 2002
Finish: March 11, 2002
Architect: Shiver-Megert & Associates
Contractor: Western Fence Company
Project Cost: $18,245.00
Multizone HVAC Unit Replacement
Location: Bonham Middle School
Start: April 26, 2002
Finish: August 12, 2002
Mechanical Engineers: Brown Consulting Engineers, Inc.
Contractor: MMM Plumbing, Heating, & Air Conditioning
Project Cost: $550,334.00
Baseball Bleacher and Pressbox Improvements
Location: Caprock, Palo Duro, and Tascosa High Schools
Start: October 24, 2002
Finish: February 22, 2003
Architect: Turner Land Architecture, LLC
Contractor: Southern Bleacher Company
Project Cost: $185,000.00
New Restroom Addition to Building 600
Location: Tascosa High School
Start: January 29, 2003
Finish: May 29, 2003
Architect: Shiver-Megert & Associates
Contractor: Wiley Hicks, Jr., Inc.
Project Cost: $71,450.00
Multizone HVAC Unit Replacement
Location: Amarillo High School
Start: January 7, 2003
Finish: August 4, 2003
Mechanical Engineers: Brown Consulting Engineers, Inc.
Contractor: Plains Plumbing
Project Cost: $1,141,750.00